Summit Eden Phase 1C

Address:
Powder Mountain, Eden, UT, 84310
Project Type:
Subdivisions
Sub Type:
Subdivisions
Created By:
Created On:
9/27/2013
Project Status:
Approved
Status Date:
1/27/2014
File Number:
UVS9241C
Project Manager

Application

This submittal of Summit at Powder Mountain Phase 1C replaces the previous submittal for Phases 1A, 1B, 1C, and 1D.  Each of the four phases have been resubmitted and entered as new and separate projects in Miradi.  Each project will be reviewed individually.


Property Address
Powder Mountain
Eden, UT, 84310

Property Owner

--

Representative

--

False
0
0
0
72
Powder Mountain Water & Sewer District
Powder Mountain Water & Sewer District
Powder Mountain Water & Sewer District
,

Parcel Number
230120032 - County Map
230120052 - County Map

Building Description Square Feet Valuation

Contractor Type Name Contact Address


Documents

List of project documents. Review documents can be found under the Review tab.

Document Name Date Uploaded
Options
Annexation Plat
Application
Attestation
Cost Estimate
Culinary Water Will-Serve
Engineered Plans
Final Recorded Plat
Geologic Hazards Evaluation
Geotechnical Evaluation
Notice of Decision
Open Space Preservation Plan
Other
Original RECORDED_Ph1C_Scriveners_Affidavit.pdf 12/18/2014
Original RECORDED_Ph1C_PUEs_20141031.pdf 12/18/2014
Original RECORDED_Parcel_G_PUE_20141119.pdf 12/18/2014
Original 7-RECORDED_Non-Exclusive_Public_Utility_Easement_PhC_20140903_1.pdf 11/3/2014
Original 2014-09-15_-_Summit_Eden_Phase_1C-Rev3.pdf 9/24/2014
Original DDW_conditional_approval_2014-09-08.pdf 9/12/2014
Review 1C_August_2014_Review_Comments.pdf 8/25/2014
Original 2014-07-31_-_Summit_Eden_-_Phase_1C-Rev2.pdf 8/20/2014
Review Fire_Flow_Requirements_8-3-2014.pdf 8/3/2014
Original 2014-05-21_-_Phase_1C.pdf 7/8/2014
Original pre-con_meeting_summary.pdf 7/2/2014
Review Road_design_criteria_email_correspondence.pdf 6/19/2014
Original Exhibits_-_CC_Staff_Report_Summit_Eden.pdf 1/24/2014
Original CC_Staff_Report_Summit_Eden.pdf 1/24/2014
Original 1C_Plat_20140114.pdf 1/15/2014
Review CPR-_Summit_at_Powder_Mountain_Phase_1C--_Weber_Fire_District_Review_2.pdf 1/14/2014
Review Ph1C_Plat_20140106-1.pdf 1/9/2014
Original Ph1C_Response_to_Survey_Review.pdf 1/7/2014
Original Ph1C_Plat_20140106.pdf 1/7/2014
Original Ph1C_Response_to_Eng_Review-1.pdf 1/7/2014
Review Ph1C_Plat_20131216.pdf 12/27/2013
Original Summit_Eden_at_Powder_Mtn_Addresses.xlsx 12/27/2013
Original Ph1C_Response_to_Eng_Review.pdf 12/18/2013
Original Ph1C_Plat_20131216.pdf 12/18/2013
Original Ph1C_Escrow_Estimate_20131218.pdf 12/18/2013
Original Ph1C_Construction_Dwgs_20131217.pdf 12/18/2013
Review Ph1C_Plat_12.4.13.pdf 12/11/2013
Original Ph1D_Ph1C_Drainage_Analysis_Report_20131205.pdf 12/6/2013
Original Ph1D_Ph1C_Drainage_Analysis_Appendices_20131205.pdf 12/6/2013
Original Ph1C_Plat_Response_to_Survey_Review.pdf 11/27/2013
Original Ph1C_Plat_Response_to_Eng_Review.pdf 11/27/2013
Original Ph1C_Plat_20131127.pdf 11/27/2013
Original Ph1C_Construction_Dwgs_Response_to_Eng_Review.pdf 11/27/2013
Original Ph1C_Construction_Dwgs_20131126.pdf 11/27/2013
Review MYSCAN_20131030_0005.pdf 10/30/2013
Review MYSCAN_20131030_0004.pdf 10/30/2013
Review MYSCAN_20131030_0003.pdf 10/30/2013
Review MYSCAN_20131030_0002.pdf 10/30/2013
Review MYSCAN_20131030_0001.pdf 10/30/2013
Review CPR-_Summit_at_Powder_Mountain_Phase_1C--_Weber_Fire_District_Review.pdf 10/23/2013
Review 2013-09-24_-_Phase_1C--_WEBER_FIRE_DISTRICT_REVIEWED.pdf 10/23/2013
Original Phase_1C_Exhibit_C.pdf 10/17/2013
Original Phase_1C_Exhibit_B.pdf 10/17/2013
Original Phase_1C_Exhibit_A.pdf 10/17/2013
Original OVPC_Staff_Report_-_Summit_at_Powder_Mountain_Phase_1C.pdf 10/17/2013
Original Summit_at_Powder_Mountain_Phase_1C_-_Application.pdf 9/27/2013
Original Phase_1C.pdf 9/27/2013
Original Phase_1C__1D_Drainage_Analysis_2013-09-24.pdf 9/27/2013
Original 2013-09-24_-_Phase_1C.pdf 9/27/2013
Preapplication Meeting Notes
Proposed Final Plat
Proposed Preliminary Plan
Public Street Connectivity Plan
Receipt
Response to Review Agencies
Secondary Water Will-Serve
Septic Feasibility
Sewer Will-Serve
Staff Report
Time Extension
Title Report
Traffic Study/Plan
Well Approval
Uncategorized Documents

Comments

Have a question? Leave a comment, your comment will be emailed to all project followers.

Sean Wilkinson - 3/10/2014
Summit Eden Phase 1C was approved by the Weber County Commission on January 21, 2014 and recorded on January 27, 2014. The recorded subdivision plats, agreements, easements, and other documents are available from the Weber County Recorder's Office.
Dana Shuler - 11/7/2013
Upon beginning my review of phase 1C, serious grading issues were discovered. A meeting with Russ Watts and team on 11-06-2013 to discuss the issues. Subsequent email correspondence from Russ directed us to put a hold on 1C for now and move on to 1D.
Scott Slater - 10/9/2013
QGC does not have facilities near development
Paul De Long - 10/3/2013
There are no pathways on the plat plan therefore the subdivision does not meet the pathways requirements of Weber County.
Karl Sewell - 9/30/2013
RMP - line extension will be in accordance with current tariff and regulations.
Sue Morgan - 9/27/2013
We will not be bussing from this area. All students will neeed to access the bus from our current stops at Juniper and Wolf Creek Dr.

Reviews

To access review documents, click on the individual review and the corresponding review documents will be listed under the review.


List of All Reviews

Engineering Review 8

Approved

Dana Shuler 12/18/2014
Engineering Review 7

Not Approved

Dana Shuler 10/1/2014
Weber Fire District Review- August 2014 Revisions

Approved

N/A N/A 8/25/2014
Engineering Review 6

Not Approved

Dana Shuler 8/23/2014
Fire Flow

Approved

N/A N/A 8/3/2014
Weber Fire District- Review July 2014

Not Approved

N/A N/A 7/14/2014
Engineering Review 5

Not Approved

Dana Shuler 6/19/2014
Survey Review 1-16-14

Approved

N/A N/A 1/16/2014
Weber Fire District Review - 2

Approved

N/A N/A 1/14/2014
Engineering Review 4

Approved

Dana Shuler 1/17/2014
Survey review 1-9-14

Not Approved

Weber County Surveyor's Office Trevor Hatch 1/9/2014
Engineering Review 3

Not Approved

Dana Shuler 1/3/2014
Survey Review 12-27-13

Not Approved

Weber County Surveyor's Office Trevor Hatch 12/27/2013
Engineering Review 2

Not Approved

Dana Shuler 12/12/2013
Survey Review 12-11-13

Not Approved

Weber County Surveyor's Office Trevor Hatch 12/11/2013
Engineering Review 1

Not Approved

Dana Shuler 11/20/2013
Property Taxes

Approved

Carolyn Laird 11/1/2013
Survey Review 10-30-13

Not Approved

Weber County Surveyor's Office Trevor Hatch 10/30/2013
Weber Fire District Review

Not Approved

N/A N/A 10/23/2013

Followers

All followers will be notified of new documents, comments, and reviews to the project.

Name Date Added
Options
Jared Andersen 1/1/0001
Gay Browning 1/1/0001
Ryan Cathey 1/1/0001
donald eatmon 1/1/0001
Rick Everson 1/1/0001
Trevor Hatch 1/1/0001
Carolyn Laird 1/1/0001
Miranda Menzies 1/1/0001
Dana Shuler 1/1/0001
Russ Watts 1/1/0001

Payments

List of all invoices tied to project.

Area Fees

List of estimated fees for this project.

Estimated Fee Total: $0