Taylor Landing Cluster Subdivision

Address:
4000 W 2200 S, Ogden, UT, 84401
Project Type:
Subdivisions
Sub Type:
Subdivisions
Created By:
Created On:
3/11/2020
Project Status:
Accepted
Status Date:
4/24/2020
File Number:
2020 LVT 0311
Project Manager

Application

Sunset Meadows Cluster Subdivision

Property Address
4000 W 2200 S
Ogden, UT, 84401

Property Owner
3900 WEST TAYLOR PARTNERS LLC DOUG NOSLER, MGR
801-644-6736
jessicap@sierrahomes.com

Representative
Jessica Prestwich
801-644-6736
jessicap@sierrahomes.com

False
A-1
Sunset Meadows Cluster
156
0
0
Taylor-West Weber Water District
Not Applicable
Central Weber Sewer
,

Parcel Number
150780001 - County Map

Building Description Square Feet Valuation

Contractor Type Name Contact Address


Documents

List of project documents. Review documents can be found under the Review tab.

Document Name Date Uploaded
Options
Annexation Plat
Application
Original Application and Receipt.pdf 3/11/2020
Attestation
Cost Estimate
Culinary Water Will-Serve
Revision Sunset-Culinary will serve.pdf 4/13/2020
Original Water.pdf 3/11/2020
Engineered Plans
Revision TaylorLandingPh1Civil8-2020.pdf 8/19/2020
Final Recorded Plat
Geologic Hazards Evaluation
Geotechnical Evaluation
Revision SunsetMeadows_SoilAssessment_041620.pdf 4/17/2020
Revision geotechnical study.pdf 3/12/2020
Notice of Decision
Revision Preliminary_Notice of decision_LVT031120.pdf 5/18/2020
Open Space Preservation Plan
Revision Master Open Space Preservation Plan.pdf 4/14/2020
Revision Phase 1&2 Open Space Plan.pdf 4/14/2020
Revision Phase 3 Open Space Plan.pdf 4/14/2020
Revision Phase 4&5 Open Space Plan.pdf 4/14/2020
Other
Revision Weber County Appeal.pdf 5/18/2020
Revision Open space narrative - sunset meadows.pdf 3/31/2020
Preapplication Meeting Notes
Proposed Final Plat
Revision TAYLOR LANDING PLAT 9-15-20 SierraSuncrestEquestrian_dwg_Sunset MeadowsPh1FinalV6.pdf 9/15/2020
Proposed Preliminary Plan
Revision The Meadows-Revised 05012020.pdf 5/1/2020
Revision #4 SunsetMeadowsPrelimPlat.pdf 3/12/2020
Revision #5 SunsetMeadowsPhasing.pdf 3/12/2020
Public Street Connectivity Plan
Receipt
Revision Appeal Receipt.pdf 5/18/2020
Response to Review Agencies
Revision Written Responses to Planning Review #1.docx 5/1/2020
Secondary Water Will-Serve
Revision Sunset-Secondary will serve.pdf 4/13/2020
Septic Feasibility
Sewer Will-Serve
Revision Taylor landing annex record.pdf 6/1/2022
Revision Sunset-Sewer will serve.pdf 4/13/2020
Original Sub.pdf 3/11/2020
Staff Report
Revision Staff Report - 06162020 CC - Taylor Landing Preliminary Subdivision Appeal_FINAL W-Exhibits.pdf 6/11/2020
Time Extension
Title Report
Original Title Ins.pdf 3/11/2020
Traffic Study/Plan
Well Approval
Uncategorized Documents
Review TaylorLandingPh1_Engineering_Review_Sept2020.pdf 9/3/2020
Review 20200414_1st Redline Prelim_ Phase 1&2 Open Space Plan.pdf 4/24/2020
Review 20200414_1st Redline Prelim_Phase 3 Open Space Plan .pdf 4/24/2020
Review 20200414_1st Redline Prelim_Phase 4&5 Open Space Plan .pdf 4/24/2020
Review review.pdf 4/7/2020
Review Sunset_Meadows_Engineering_Review_March2020.pdf 3/27/2020

Comments

Have a question? Leave a comment, your comment will be emailed to all project followers.

Scott Perkes - 10/22/2021

@Ryan Rodgers - Addressing has been assigned to each lot within Phase 1A and can be referenced on the recorded dedication plat plat. You can obtain a copy of the recorded dedication plat here:

http://www3.co.weber.ut.us/ded_plats.php

(simply search by "Taylor Landing")

Ryan Rogers - 10/19/2021

Have the addresses been identified for Taylor Landing Phase 1 ? TIA

Scott Perkes - 9/21/2020

Final review of each phase's final plat and cuvil plans for this project will be reviewed through a dedicated Frontier project page. Phase 1A's Frontier page can be found here:

https://frontier.co.weber.ut.us/p/Project/Index/11844#info

Please use this dedicated link to continue the review of Phase 1A.

 

Scott Perkes

Planner - Weber County Planning Division

Jessica Prestwich - 9/15/2020

I have uploaded the proposed final plat for phase 1a. Please review and send me your comments. Thank you

Jessica Prestwich - 8/19/2020
Phase 1 civil plans have been uploaded in the documents. Can the engineering department please review? Thanks.
Scott Perkes - 5/18/2020
The Western Weber Planning Commission voted to deny preliminary approval of the subdivision during their 5/12/2020 meeting. Following this decision, the applicant has submitted a formal appeal for County Commission consideration. This appeal will be scheduled for an upcoming (TBD) County Commission meeting.
Scott Perkes - 5/4/2020
They Surveyor's office has indicated that both "Sunset Meadows" and "The Meadows" name have been used by other existing developments. As such, the name is being changed to Taylor Landing.
Scott Perkes - 4/24/2020
The applicant has submitted a complete open space preservation plan and all necessary will-serve letters required to complete the subdivision application.
Scott Perkes - 4/21/2020
This project is tentatively scheduled for the 5/12/2020 Western Weber Planning Commission for preliminary review. Planning review of currently submitted plans will be uploaded shortly.
Jessica Prestwich - 4/14/2020
Scott Perkes, there is now an open space preservation plan along with open space preservation plats. We have 3 separate plats, Phase 1&2, Phase 3 and Phase 4. I hope this helps to see the Open space preservation plan that we have in place. Thank you!
Jessica Prestwich - 4/14/2020
Darrel Woodruff, I have uploaded new plats. Please take a look and let me know if there are any updates needed. Thank you!
Darrel Woodruff - 3/27/2020
Surveyors office will review when a subdivision survey plat is uploaded.
Scott Perkes - 3/19/2020
Per LUC 108-3-3(c) - This application must include an Open Space Preservation Plan as outlined in LUC 108-3-5 in order to begin the agency review process.

Reviews

To access review documents, click on the individual review and the corresponding review documents will be listed under the review.


List of All Reviews

Engineering

Not Approved

Weber County Engineering Chad Meyerhoffer 9/3/2020
Hooper Irrigation

Not Approved

Public Greg Seegmiller 8/7/2020
Planning Review #1

Not Approved

Weber County Planning Scott Perkes 4/24/2020
Survey 1st preliminary review phases 1 thru 5

Not Approved

Weber County Surveyor's Office Darrel Woodruff 4/24/2020
Ryan Rogers

Not Approved

Public Ryan Rogers 4/15/2020
Fire Review

Approved

Weber Fire District David Reed Weber Fire District 4/7/2020
Engineering

Not Approved

Weber County Engineering Chad Meyerhoffer 3/27/2020
Planning Pre-Review

Not Approved

Weber County Planning Scott Perkes 3/30/2020
Shirley / Treasurer

Approved

Shirley Robinson 3/19/2020

Followers

All followers will be notified of new documents, comments, and reviews to the project.

Name Date Added
Options
Steve Burton 3/13/2020
Steve Collier 3/13/2020
Dennis Flinders 3/13/2020
Kevin Hill 3/13/2020
Justin Kuester 7/10/2020
Chad Meyerhoffer 3/13/2020
Wayne Nelson 4/15/2020
Scott Perkes 3/19/2020
Jessica Prestwich 3/24/2020
Bahy Rahimzadegan 3/13/2020
Ryan Rogers 3/13/2020
Greg Seegmiller 3/13/2020
Karl Sewell 3/13/2020
Scott Slater 3/13/2020
Marshae Stokes 1/13/2022
David Reed Weber Fire District 3/13/2020

Payments

List of all invoices tied to project.

Area Fees

List of estimated fees for this project.

Estimated Fee Total: $0