Melanie Lane Storm Drain

Address:
2741 E Melanie Lane, Uintah, UT,
Maps:
Project Type:
Engineering Projects
Sub Type:
Engineering Projects
Created By:
Created On:
8/31/2011
Project Status:
Submitted
Status Date:
12/14/2011
File Number:
2011-14
Project Manager

Application

A storm drain pipe will be installed along Melanie Lane connecting the two catch basins on the North side of the road in an effort to minimize the water which runs through the southerly culvert toward Woodland Drive. This project is in response to complaints from residents which live in the area between Melanie Land and Woodland Drive.


Property Address
2741 E Melanie Lane
Uintah, UT,

Property Owner

--

Representative

--

False
0
,

Parcel Number

Building Description Square Feet Valuation

Contractor Type Name Contact Address


Documents

List of project documents. Review documents can be found under the Review tab.

Document Name Date Uploaded
Options
Other
Original compaction_test.jpg 10/17/2012
Original 2011-14-Cover_Sheet.pdf 10/1/2012
Original 2011-14-Details.pdf 10/1/2012
Original 2011-14-Plan__Profile.pdf 10/1/2012
Original Manhole_Stacksheets.pdf 10/1/2012
Original MHU-1060_A-1180.pdf 10/1/2012
Original PRESS-SEAL_PRO_STICK_SUBMITTAL.pdf 10/1/2012
Original FLAT_LID_REINFORCEMENT.pdf 10/1/2012
Original 60_Inch_Flat_Base_Manhole.pdf 10/1/2012
Original 48_Inch_Flat_Base_Manhole.pdf 10/1/2012
Original Purchase_Order_Agreement.pdf 9/20/2012
Original Invitation_to_Bid_Signed.pdf 9/20/2012
Original Cert_of_Ins_-_Weber_County.pdf 9/19/2012
Original Performance_Bond.pdf 9/19/2012
Original Payment_Bond.pdf 9/19/2012
Original Signed_Notice_of_Award.pdf 9/19/2012
Original Authorization_to_enter_property_Egan.pdf 4/16/2012
Original Authorization_to_enter_property_Guay.pdf 4/16/2012
Uncategorized Documents

Comments

Have a question? Leave a comment, your comment will be emailed to all project followers.

N/A - 12/3/2012
Contractor emailed me today asking for the status on his check. Angela said his check should go out tomorrow.
N/A - 11/28/2012
The grate on the catch basin has been fixed and approved by Jared. I've asked Angela to pay the previously submitted invoice.
N/A - 11/7/2012
I did a site visit today and need to talk with Jared before I approve the invoice
N/A - 11/5/2012
Project has been completed. Today I received 2 change orders and a final invoice for the project. I will do a site visit later this week before approving the change orders or the invoice.
N/A - 10/3/2012
I spoke to Todd with Robertson Precast today. We discussed each of the manholes and he will be preparing new stack sheets for my approval based on our conversation.
Chad Meyerhoffer - 10/1/2012
Robertson Mfg submitted some drawings I put them in the project folder.
N/A - 9/20/2012
Pre-construction meeting was held on-site today. The contractor has asked for our field crew to locate manholes for him. He signed the Purchase Order Agreement & the Invitation to Bid. He said he will be starting the first week or two of October and will be done by the end of the month.
N/A - 9/19/2012
Yesterday I sent the interns to Mr Gauy's home to give them my business card and ask them to call me regarding the easement as I've been unable to reach them. I received a message from them with 2 valid phone numbers. I was able to reach Mr. Guay this morning and have sent him the draft easement for review. I sent Mr. Egan a follow up email regarding the draft easement I sent him on 9-5-12 as I've heard nothing from him regarding the easement. Notice of award has been signed, the performance & payment bonds and certificate of liability insurance have been submitted. I still need the contract signed. The pre-construction meeting is scheduled for 9-20-12.
N/A - 9/10/2012
Project has been awarded to Accurite Excavation.
N/A - 9/10/2012
There were 3 bidders on this project. I will have an award of the bid out by then end of today.
N/A - 8/28/2012
Bid opening will be September 6th at 2:00
N/A - 8/22/2012
Bid package was sent to purchasing this morning.
N/A - 8/21/2012
Drawings and bid documents are done, waiting for engineering review before sending out to bid.
N/A - 8/15/2012
I received the Drainage Analysis from CRS this morning and have sent drawing to Larry to write an easement for the drainage. Once I have the easement I will meet with the attorney's office to determine the proper wording to obtain a drainage, maintenance and temporary construction easement. A meeting with the property owner's will be held to discussed required improvements to the ditch.
N/A - 8/14/2012
Drawings and bid documents are mostly done. Waiting on CRS for open channel flow data to finish.
N/A - 6/22/2012
I received a .csv file from Larry today on the drainage ditch
N/A - 6/19/2012
I spoke to Larry yesterday about the survey of the drainage ditch. He indicated the field work has been done, he just needs to do his thing to it before he can give it me.
N/A - 4/23/2012
I just spoke to Larry about tieing down the drainage ditch, he is concerned about the foliage and thinks it will be pretty time consuming to do. He said he could get someone out there to start probably next week sometime.
Michael Tuttle - 4/16/2012
We met with both of the property owners on site, Friday April 13, 2012. I have attached the files from Kristian Guay and Rodney Egan granting us access onto their properties to get the survey work done.
N/A - 3/22/2012
Easement Exhibit was completed today, Mike will get an appointment with the home owner to discuss getting a letter from them stating they will give us permission to survey the drain ditch on their property and make our prescriptive easement a matter of record.
N/A - 2/29/2012
I have received additional survey points but I'm waiting on the correct version of cad file to complete my design.
N/A - 1/31/2012
I followed up with Larry about the additional survey info needed to complete this project. He indicated that it would be after the 7th and that he has another project to do for me as well. He assured me he hasn't forgotten about my project and will let me know when he's gathered the info I need
N/A - 1/23/2012
After getting the initial design completed, it came to my attention that we needed to do something different at the end. Mike and Chad spoke to the home owner about granting us an easement along his ditch. I've requested that Larry get some additional information for me, i.e., a sewer manhole, trees on the South side of the road and a couple ditch shots. Once I get that information back I will revise my design, prepare an exhibit for Mike to show the homeowner in an effort to get an easement.
N/A - 11/16/2011
I have the survey data from Larry and am currently working on the design.
Michael Tuttle - 11/15/2011
Talked to Nate Pierce today, 2011-11-15, and he said to go ahead and get the work bid out and completed. We'll be paying for it out of the Stormwater Fund.
N/A - 10/17/2011
I called Great Basin for a proposal on the survey portion of this project.
N/A - 8/31/2011
I spoke to Larry yesterday about getting a quick topog of the effected area. He is short handed right now, but added it to his to do list. I indicated that it wasn't a rush, we just needed to get the pipe in the ground prior to winter.

Reviews

To access review documents, click on the individual review and the corresponding review documents will be listed under the review.

Followers

All followers will be notified of new documents, comments, and reviews to the project.

Name Date Added
Options
Michael Tuttle 1/1/0001