Verizon Wireless is proposing to install an unmanned communication facility consisting of antennas mounted to a new 85' tall monopine with equipment located inside a new 12' x 26' prefabricated equipment building enclosed with a six foot tall chain link fence with three strands of barbed wire.
Some changes have been made to the design and site plan location for this proposed cell site. With the new location, the pole type will be a 50 foot monopole. Please refer to the new plans as of Sept. 2012.
Parcel Number |
---|
130750006 - County Map |
Building Description | Square Feet | Valuation |
---|
Contractor Type | Name | Contact | Address |
---|
List of project documents. Review documents can be found under the Review tab.
Document Name | Date Uploaded |
Options
|
|
---|---|---|---|
Building renderings | |||
Easement documents | |||
Engineered Plans | |||
Geologic hazards study | |||
Geotechnical report | |||
Landscaping Plan | |||
Narrative | |||
Notice of decision | |||
Other | |||
Original Time_Extension_Notice_of_Decision.pdf | 12/19/2013 | ||
Original SAL_Peery_Camp_extension_of_time.pdf | 12/10/2013 | ||
Original Notice_of_Decision.pdf | 1/18/2013 | ||
Original Final_Site_Plans.pdf | 11/26/2012 | ||
Original NEPA_Letter_Peery_Camp.pdf | 9/18/2012 | ||
Original Site_Plan_with_photo.pdf | 9/18/2012 | ||
Original Site_Plan.pdf | 9/18/2012 | ||
Original Prelim_Site_Plan.pdf | 9/18/2012 | ||
Original SAL_PEERY_CAMP_Drawings_set_2.pdf | 1/12/2012 | ||
Original Sal_Peery_Camp_-_Final_PS_2b.jpg | 12/7/2011 | ||
Original Sal_Peery_Camp_-_Final_PS_1b.jpg | 12/7/2011 | ||
Original CIMG0382.jpg | 10/24/2011 | ||
Original CIMG0381.jpg | 10/24/2011 | ||
Original CUP_2011-06_Sal_Perry_Camp_Site_Plan.pdf | 10/14/2011 | ||
Original CUP_2011-06_Sal_Peery_Camp_Application.pdf | 10/14/2011 | ||
Permits issued | |||
Planning staff report | |||
Signage Plan | |||
Site Plan | |||
Time Extension | |||
Water and Wastewater Plan | |||
Uncategorized Documents |
To access review documents, click on the individual review and the corresponding review documents will be listed under the review.
Planning Divison Staff Report |
Approved |
N/A | N/A | 12/20/2013 |
Planning Division Staff Report |
Approved |
N/A | N/A | 12/6/2012 |
Engineering |
Not Approved |
Weber County Engineering | Chad Meyerhoffer | 9/19/2012 |
Planning Division Staff Report |
Not Approved |
N/A | N/A | 9/18/2012 |
Staff Report to the Ogden Valley Planning Commission |
Not Approved |
N/A | N/A | 2/22/2012 |
Planning Review |
Not Approved |
N/A | N/A | 1/17/2012 |
Engineering |
Not Approved |
Weber County Engineering | Chad Meyerhoffer | 1/17/2012 |
Fire Review |
Approved |
Weber Fire District | Ted Black | 12/8/2011 |
Fire Review |
Approved |
Weber Fire District | Ted Black | 10/31/2011 |
Engineering |
Approved |
Weber County Engineering | Chad Meyerhoffer | 10/24/2011 |
Building Inspection Review |
Approved |
Craig Browne | 10/17/2011 |
All followers will be notified of new documents, comments, and reviews to the project.
Name | Date Added |
Options
|
---|---|---|
Ted Black | 1/1/0001 | |
Craig Browne | 1/1/0001 | |
doug kofford | 1/1/0001 | |
Doug Kofford | 1/1/0001 | |
Chad Meyerhoffer | 1/1/0001 |
List of all invoices tied to project.
Comments