Lindsley Ranch Subdivision

Address:
1625 S 7500 West, Ogden, UT, 84401
Project Type:
Subdivisions
Sub Type:
Subdivisions
Created By:
Created On:
7/8/2011
Project Status:
Approved
Status Date:
5/21/2012
File Number:
LVL 07-08-11
Project Manager

Application

1 lot standard subdivision.


Property Address
1625 S 7500 West
Ogden, UT, 84401

Property Owner

--

Representative

--

False
0
0
0
3
West Warren-Warren Water & Sewer
Warren Irrigation Company
Septic
,

Parcel Number
100430072 - County Map

Building Description Square Feet Valuation

Contractor Type Name Contact Address


Documents

List of project documents. Review documents can be found under the Review tab.

Document Name Date Uploaded
Options
Annexation Plat
Application
Attestation
Cost Estimate
Culinary Water Will-Serve
Engineered Plans
Final Recorded Plat
Geologic Hazards Evaluation
Geotechnical Evaluation
Notice of Decision
Open Space Preservation Plan
Other
Original lindsley_ranch_deferral.pdf 9/19/2012
Original lindsley_ranch_agreement.pdf 9/19/2012
Original Signed_Subdivision_Improvement_Agreement.pdf 5/22/2012
Original Signed_Deferral_Agreement.pdf 5/22/2012
Original Final_Plat-4.pdf 9/21/2011
Review Reeves_Lindsley_Ranch_Subd_2nd_review.pdf 9/19/2011
Original engineers_comment_letter_9-12-11.pdf 9/12/2011
Original Final_Plat-3.pdf 9/12/2011
Original Improvement_Plans-1.pdf 9/12/2011
Original Final_Plat-1.pdf 9/6/2011
Original Improvement_Plans.pdf 9/6/2011
Original Warren_Irrigation_Approval_Letter.pdf 8/24/2011
Original Warren_Canal_Approved_Drawing.pdf 8/24/2011
Review Reeves_Lindsley_Ranch_Subd_1st_review.pdf 8/9/2011
Original Property_Owner_Notifications.pdf 8/2/2011
Original Final_Plat-2.pdf 7/22/2011
Original Ditch_Improvements.pdf 7/22/2011
Original Comments_From_Reeves_on_Engineering_Review.pdf 7/22/2011
Original Final_Plat.pdf 7/11/2011
Original Application.pdf 7/8/2011
Preapplication Meeting Notes
Proposed Final Plat
Proposed Preliminary Plan
Public Street Connectivity Plan
Receipt
Response to Review Agencies
Secondary Water Will-Serve
Septic Feasibility
Sewer Will-Serve
Staff Report
Time Extension
Title Report
Traffic Study/Plan
Well Approval
Uncategorized Documents

Comments

Have a question? Leave a comment, your comment will be emailed to all project followers.

Sean Wilkinson - 5/22/2012
The subdivision plat and other agreements were recorded on May 21, 2012.
Sean Wilkinson - 5/21/2012
The mylar plat has all of the required signatures and is ready to be recorded. All of the required agreements have been signed except for the deferral agreement, which is prepared and ready for a signature. The County Commission approved the subdivision on May 15th.
Sean Wilkinson - 5/10/2012
Sean Wilkinson is now the project manager for this project.
Justin Morris - 5/8/2012
Ben Hatfield is now the project manager for this project.
N/A - 5/7/2012
Cliff Bell brought in the escrow check, mylar and SWCAP. He spoke to Sean Wilkinson and was told he would be on the agenda for the County Commission meeting next Tuesday. Mylar is waiting for the County Engineer to sign it.
N/A - 5/3/2012
Cliff Bell was in today, he gave me the SWPPP and I gave him the SWCAP to fill out and return as well as a blank escrow certificate. He asked me to set up a meeting Jared to discuss the escrow amount. When he comes in for the meeting he will have an approval from Ted Black and the mylar, hopes to get on the agenda asap.
N/A - 4/30/2012
I spoke to Cliff Bell on the phone this morning about getting the ditch piped. I informed him that I've spoken to the County Engineer and the only way we can allow him to pull a building permit or record the mylar is to put up an escrow for the materials and installation (even though he's already purchased the materials) or get the improvements installed. He isn't able to install the improvements until October due to the water being turned into the ditch. As we were talking, he indicated the ditch was on private property and not in the right of way. I told him to get something from his surveyor showing me that. If the ditch is not in the County right of way, I can't required it to be piped. He said he would get that information for me.
N/A - 4/10/2012
I met Cliff Bell on site, we reviewed the plans for piping the irrigation ditch. Water will be turned into the ditch any day so he asked if he could buy all the materials and put up the escrow for the labor. I told him that was fine, but when I got back to the office I was told that wasn't okay. We will make an exception in this case and let him do what I said was okay but he won't be able to pull a building permit until the improvements are installed. I called Cliff and left him a message about my mistake.
N/A - 4/6/2012
I spoke to Cliff Bell and Kent Buie, Cliff will be finishing up this project and Kent will be finishing the North Fields project.
Jack Haight - 4/4/2012
Approval for the printing of Mylar's was given by this office back on the 14th of September 2011....See the review section.
N/A - 4/4/2012
I spoke to Cliff Bell this morning, he is now working on this project and has another buyer. He called to find out where the project stands and what is left to be done. I will be meeting him on site today to go over everything.
Justin Morris - 11/4/2011
I received the following reply from Kent Buie on November 1, 2011: Mark LIndsley, our buyer, failed to close. We are holding the mylar of a while to see if he circles back after the first of the year. Without a buyer we can not justify installing improvements. BTW - tried to reply to Miradi but could not log in nor reset username PW without success.
Justin Morris - 11/1/2011
Has anyone seen a mylar for this?
Jack Haight - 9/19/2011
Completed my 2nd review of Lindsley Ranch. Emailed it to Chris @ Reeves and Assoc....9/19/2011
Justin Morris - 9/6/2011
I added two files for Engineering and Surveying to review: Improvement Plans.pdf and Final Plat-1.pdf.
Justin Morris - 8/12/2011
There will be a special meeting for the Western Weber Planning Commission on August 16, 2011 at 5:00 PM.
Justin Morris - 8/10/2011
There was no quorum for the Western Weber Planning Commission meeting last night. There might be a special meeting next week. I'll post an update once I know the date and time.
Jack Haight - 8/9/2011
Completed the 1st survey review of Lindsley Ranch Subd. Emailed it to Nick Anderson with Reeve and Assoc. 8/9/11
Michael Tuttle - 7/27/2011
I just talked to Kent Buie on the phone about the escrow. He doesn't want to escrow for the all the improvements. I told him that after final approval of the plans, and a pre-construction meeting he can install the improvements with all required inspections. If they do that then they only have to escrow the 10% contingency for the warranty period.
Justin Morris - 7/26/2011
Michelle, the will serve letter is the fourth page in the Application.pdf file. You can find it under the Files tab.
Michelle Cooke - 7/26/2011
If culinary water is being provided by West Warren, we need a will serve letter form the water company
Justin Morris - 7/18/2011
On 2011-07-08 at 4:28 PM I emailed Chris Cave at Reeve and Associates informing him that this project is available for him to follow.
Jack Haight - 7/11/2011
Plotted the PDF file this morning and put on my schedule for review 7/11/11
Justin Morris - 7/11/2011
Robert Kunz at Reeve and Associates emailed me the final plat this morning and I added it to the project.
Justin Morris - 7/8/2011
I called Kent Buie and requested electronic copies of the subdivision plat.

Reviews

To access review documents, click on the individual review and the corresponding review documents will be listed under the review.


List of All Reviews

Survey Review_3rd review

Approved

Jack Haight 10/14/2011
Engineering Review 4

Approved

N/A N/A 9/21/2011
Survey Review_2nd review

Not Approved

Jack Haight 9/19/2011
Engineering Review 3

Not Approved

N/A N/A 9/9/2011
drinking water

Approved

Michelle Cooke 8/23/2011
Survey Review_1st review

Not Approved

Jack Haight 8/9/2011
Staff Report to the Western Weber County Planning Commission

Approved

Justin Morris 8/2/2011
Engineering Review 2

Not Approved

N/A N/A 7/27/2011
Bussing

Approved

Kristen Kearl 7/21/2011
Fire Review

Not Approved

Weber Fire District Ted Black 7/21/2011
Engineering Review

Not Approved

N/A N/A 7/12/2011
Property Taxes

Approved

Carolyn Laird 7/11/2011

Followers

All followers will be notified of new documents, comments, and reviews to the project.

Name Date Added
Options
Cliff Bell 1/1/0001
Ted Black 1/1/0001
Kent Buie 1/1/0001
chris cave 1/1/0001
Michelle Cooke 1/1/0001
Brian Cowan 1/1/0001
Jack Haight 1/1/0001
Candice Kunz 1/1/0001
Carolyn Laird 1/1/0001
Justin Morris 1/1/0001