Taylor Landing Cluster Subdivision Phase 2

Address:
4000 W 2200 S, Ogden, UT, 84401
Project Type:
Subdivisions
Sub Type:
Subdivisions
Created By:
Created On:
10/30/2020
Project Status:
Accepted
Status Date:
10/30/2020
File Number:
LVT031120
Project Manager

Application

Taylor Landing Cluster Subdivision Phase 2

Property Address
4000 W 2200 S
Ogden, UT, 84401

Property Owner
3900 WEST TAYLOR PARTNERS LLC DOUG
801-644-6736
jessicap@sierrahomes.com

Representative
Jessica Prestwich
801-644-6736
jessicap@sierrahomes.com

False
A-1
Taylor Landing Cluster Subdivision Phase 2
20
0
0
Taylor-West Weber Water District
Hooper Irrigation Company
Central Weber Sewer
3997 W 2100 S
,

Parcel Number
150780110 - County Map

Building Description Square Feet Valuation

Contractor Type Name Contact Address


Documents

List of project documents. Review documents can be found under the Review tab.

Document Name Date Uploaded
Options
Annexation Plat
Application
Attestation
Cost Estimate
Revision 2021.10.18 - Next Construction - Quote Proposal Taylor landing 2 R2.pdf 1/20/2022
Culinary Water Will-Serve
Revision 2022.23.02 TWWW Final Will Serve Taylor Landing Phase 2.pdf 2/23/2022
Revision 2021.10.19 Taylor West Weber Water Will Serve Ltr Phase 2.pdf 2/17/2022
Engineered Plans
Revision TaylorLanding1and2CivilFeb2021.pdf 3/9/2021
Revision TaylorLanding1A2CivilNov2020.pdf 11/5/2020
Final Recorded Plat
Geologic Hazards Evaluation
Geotechnical Evaluation
Notice of Decision
Revision LVT031120_PH1A_PH2_Notice of Decision_Final Plat_WWPC_111020.pdf 11/10/2020
Open Space Preservation Plan
Other
Revision 2023.11.14 Taylor Landing Phase 2 TWWW Final Acceptance letter.pdf 11/14/2023
Revision 2020-WWPC_Nov_10_Final.pdf 12/7/2021
Revision CC_min_05112021.pdf 12/7/2021
Preapplication Meeting Notes
Proposed Final Plat
Revision 2022.01.27 Taylor Landing Phase 2 Final Plat.pdf 2/17/2022
Revision TAYLOR LANDING PH2 4-26-21 SierraSuncrestEquestrian_dwg_Sunset MeadowsPh1FinalV9f Ph2Plat (1).pdf 4/27/2021
Revision TAYLOR LANDING PH2 2-18-21 V__ACE 2019_SierraSuncrestEquestrian_dwg_Sunset MeadowsPh1FinalV9b Ph2Plat (1)(1).pdf 3/22/2021
Revision TAYLOR LANDING PH2 1-5-21 PLAT ACE 2019_SierraSuncrestEquestrian_dwg_Sunset MeadowsPh1FinalV9b.pdf 1/6/2021
Revision TAYLOR LANDING PH2 11-30-20 SierraSuncrestEquestrian_dwg_Sunset MeadowsPh1FinalV9a Ph2Plat (1).pdf 12/7/2020
Revision TAYLOR LANDING PH2 10-29-20.pdf 10/30/2020
Proposed Preliminary Plan
Public Street Connectivity Plan
Receipt
Revision Escrow Deposit Receipt - Taylor Landing Phase 2.pdf 5/17/2022
Response to Review Agencies
Secondary Water Will-Serve
Revision 2021.12.08 Taylor Landing Phase 2 Hooper Irrigation Will Serve.pdf 2/17/2022
Septic Feasibility
Sewer Will-Serve
Revision Taylor landing annex record.pdf 6/1/2022
Revision Sunset-Sewer will serve.pdf 6/1/2022
Staff Report
Revision LVT031120_Taylor Landing Cluster Ph-2_CC_Staff Report_FINAL.pdf 5/4/2022
Time Extension
Title Report
Traffic Study/Plan
Well Approval
Uncategorized Documents
Review 20220217_ 6th Redline_Taylor Landing Phase 2 _6N2W28NW.pdf 3/16/2022
Review 20210322_ 4th Redline_Taylor Landing Phase 2 _6N2W28NW.pdf 3/29/2021
Review TAYLOR LANDING PH2 2-18-21 V__ACE 2019_SierraSuncrestEquestrian_dwg_Sunset MeadowsPh1FinalV9b Ph2Plat (1)(1)_Planning Redlines.pdf 3/22/2021
Review 20210106_ 3rd Redline_Taylor Landing Phase 2 _6N2W28NW.pdf 1/15/2021
Review 1 - Monument Improvement Agreement Letter_19.pdf 1/15/2021
Review 2 - Monument Improvement Agreement Instructions_19.pdf 1/15/2021
Review 3 - Monument Improvement Agreement_19.pdf 1/15/2021
Review W.C. Monument Inspection Sheet_19_w_Sheets.pdf 1/15/2021
Review 20201207_ 2nd Redline_Taylor Landing Phase 2 _6N2W28NW.pdf 12/21/2020
Review 1 - Monument Improvement Agreement Letter_19.pdf 12/21/2020
Review 2 - Monument Improvement Agreement Instructions_19.pdf 12/21/2020
Review 3 - Monument Improvement Agreement_19.pdf 12/21/2020
Review W.C. Monument Inspection Sheet_19_w_Sheets.pdf 12/21/2020
Review TAYLOR LANDING PH2 11-30-20 SierraSuncrestEquestrian_dwg_Sunset MeadowsPh1FinalV9a Ph2Plat (1)_Planning Redlines.pdf 12/9/2020
Review 20201030_Taylor Landing Phase 2 _Addressing.pdf 11/10/2020
Review 20201030_1st RedlineTaylor Landing Phase 2 _6N2W28NW.pdf 11/10/2020

Comments

Have a question? Leave a comment, your comment will be emailed to all project followers.

Shirley Robinson - 5/5/2022

Concerning Property Taxes, the prior parcel number 15-078-0110 is Discontinued. In my search for new parcel numbers, I have found 15-078-0176, 15-078-0179 and 15-078-0001. Are these the correct parcel numbers for this Subdivision?

Scott Perkes - 2/17/2022

The applicant has submitted an updated final plat document that addresses the most recent survey comments (Survey 4th Final Review). 

Scott Perkes - 1/20/2022

The applicant has uploaded a construction bid document associated with Phase 2 improvements.

Engineering - Please review at your earliest convenience.

Scott Perkes - 12/7/2021

Meeting minutes for the 11/10/2021 WWPC and the 05/11/2021 CC meetings have been uploaded to the Documents tab.

Scott Perkes - 4/27/2021

The applicant has uploaded an updated final plat (dated 04/26/2021) to address a minor Planning Division comment (added a temporary access easement).

Scott Perkes - 3/22/2021

The applicant has uploaded a revised final plat (dated 2/18/2021) that has addressed the last set of agency review comments. All agencies, please review to verify that all remaining comments have been addressed.

Scott Perkes - 1/6/2021

The applicant has uploaded a revised final plat (01/06/2021) that has addressed the last set of agency review comments. All agencies, please review to verify that all remaining comments have been addressed.

Scott Perkes - 12/7/2020

The applicant has uploaded a revised final plat that has addressed the last set of agency review comments. All agencies, please review to verify that all remaining comments have been addressed.

Scott Perkes - 11/10/2020

This project was approved for final approval by the Western Weber Planning Commission during their 11/10/2020 meeting. A formal notice of decision has been uploaded to the Documents tab.

Scott Perkes - 11/5/2020

Updated civil plans have been uploaded. File name: "TayorLanding1A2CivilNov2020.pdf"

Scott Perkes - 10/30/2020

The proposed final plat for Phase2 has been uploaded to the Documents tab. All review agencies please review.

Scott Perkes - 10/30/2020

Please use this Frontier project page to continue reviewing Phase 2 of the Taylor Landing Cluster Subdivision project for final plat and civil improvements.

Reviews

To access review documents, click on the individual review and the corresponding review documents will be listed under the review.


List of All Reviews

5th FinaL Review

Conditional

Weber County Surveyor's Office Darrel Woodruff 3/16/2022
Planning Review #4

Recommend Approval with Conditions

Weber County Planning Scott Perkes 2/17/2022
Survey 4th Final review

Conditional

Weber County Surveyor's Office Darrel Woodruff 3/29/2021
Planning Review #3

Recommend Approval with Conditions

Weber County Planning Scott Perkes 3/22/2021
Survey 3rd FInal Review

Conditional

Weber County Surveyor's Office Darrel Woodruff 1/15/2021
Survey 2nd FInal Review

Not Approved

Weber County Surveyor's Office Darrel Woodruff 12/21/2020
Addressing Review #2

Approved

Weber County Surveyor's Office Brett Badley 12/18/2020
Planning Review #2

Recommend Approval with Conditions

Weber County Planning Scott Perkes 12/9/2020
Fire Review

Approved

Weber Fire District David Reed Weber Fire District 11/24/2020
Survey 1st Final Review

Not Approved

Weber County Surveyor's Office Darrel Woodruff 11/10/2020
Addressing Review #1

Not Approved

Weber County Surveyor's Office Brett Badley 11/10/2020
Property Taxes

Not Approved

Shirley Robinson 12/12/2023

Followers

All followers will be notified of new documents, comments, and reviews to the project.

Name Date Added
Options
Tammy Aydelotte 7/28/2022
Steve Burton 10/30/2020
Steve Collier 10/30/2020
Dennis Flinders 10/30/2020
Kevin Hill 10/30/2020
Justin Kuester 10/30/2020
Chad Meyerhoffer 10/30/2020
Wayne Nelson 10/30/2020
Scott Perkes 10/30/2020
Jessica Prestwich 10/30/2020
Bahy Rahimzadegan 10/30/2020
Shirley Robinson 5/5/2022
Ryan Rogers 10/30/2020
Greg Seegmiller 10/30/2020
Karl Sewell 10/30/2020
Scott Slater 10/30/2020
Scott Slater 10/30/2020
Marshae Stokes 1/13/2022
David Reed Weber Fire District 10/30/2020
Darrel Woodruff 10/30/2020

Payments

List of all invoices tied to project.

Area Fees

List of estimated fees for this project.

Estimated Fee Total: $0