A conditional use permit application for the replacement of an existing water tank with a new circular concrete water reservoir. The reservoir will be an enclosed 200,000 gallon water tank, 48 feet in diameter and 16 feet tall with a portion of the tank exposed. The proposed site currently has an existing 180,000 gallon water tank that will be removed prior to the construction of the replacement reservoir and is on property owned by the Uintah Highlands Water and Sewer Improvement District. Review/Approval agencies for the project may include the State Division of Drinking Water, Weber-Morgan Health Department and the US Forest Service.
Parcel Number |
---|
061210018 - County Map |
Building Description | Square Feet | Valuation |
---|
Contractor Type | Name | Contact | Address |
---|
List of project documents. Review documents can be found under the Review tab.
Document Name | Date Uploaded |
Options
|
|
---|---|---|---|
Building renderings | |||
Easement documents | |||
Engineered Plans | |||
Geologic hazards study | |||
Geotechnical report | |||
Landscaping Plan | |||
Narrative | |||
Notice of decision | |||
Other | |||
Original CU_INDX25-2015.pdf | 2/24/2016 | ||
Original 4-7-15_Division_of_Drinking_Water_Approval.pdf | 4/9/2015 | ||
Review Maps_and_Exhibits_to_Staff_Report.pdf | 4/7/2015 | ||
Original 2015-03-25_Review_response.pdf | 4/7/2015 | ||
Original Forest_Service_Plan_Submittal.pdf | 3/19/2015 | ||
Original Project_Notification_Form.pdf | 3/19/2015 | ||
Original Geotech_Report.pdf | 3/19/2015 | ||
Original Structural_Calcs.pdf | 3/19/2015 | ||
Original Plans_and_Specs.pdf | 3/19/2015 | ||
Original CUP_2015-11_Uintah_Highlands_Reservoir_3.pdf | 3/19/2015 | ||
Permits issued | |||
Planning staff report | |||
Signage Plan | |||
Site Plan | |||
Time Extension | |||
Water and Wastewater Plan | |||
Uncategorized Documents |
To access review documents, click on the individual review and the corresponding review documents will be listed under the review.
Notice of Decision |
Approved |
N/A | N/A | 4/16/2015 |
Planning Division Staff Report to Planning Commission |
Approved |
N/A | N/A | 4/16/2015 |
Weber Fire Comments |
Approved |
N/A | N/A | 3/25/2015 |
Engineering Review 1 |
Approved |
Dana Shuler | 4/3/2015 |
All followers will be notified of new documents, comments, and reviews to the project.
Name | Date Added |
Options
|
---|---|---|
Stan Berniche | 1/1/0001 | |
Dana Shuler | 1/1/0001 |
List of all invoices tied to project.
Comments
Have a question? Leave a comment, your comment will be emailed to all project followers.