Parcel Number |
---|
210130009 - County Map |
210130001 - County Map |
Building Description | Square Feet | Valuation |
---|
Contractor Type | Name | Contact | Address |
---|
List of project documents. Review documents can be found under the Review tab.
Document Name | Date Uploaded |
Options
|
|
---|---|---|---|
Annexation Plat | |||
Revision receipt.pdf | 5/22/2023 | ||
Application | |||
Attestation | |||
Cost Estimate | |||
Culinary Water Will-Serve | |||
Engineered Plans | |||
Revision 2023.09.21 - Gateway P1 Imp.pdf | 9/26/2023 | ||
Revision 2023.06.29 - Gateway P1 Imp.pdf | 7/3/2023 | ||
Revision Lot 104 drainage calcs.pdf | 7/3/2023 | ||
Revision 2023.06.12 - Gateway P1 Imp.pdf | 6/12/2023 | ||
Final Recorded Plat | |||
Geologic Hazards Evaluation | |||
Geotechnical Evaluation | |||
Revision 1210067 Letter, Geologic Hazard Study.pdf | 6/29/2023 | ||
Notice of Decision | |||
Revision Notice of Decision_Final_10.04.2023_Phases 1a-1d.pdf | 10/24/2023 | ||
Open Space Preservation Plan | |||
Other | |||
Revision Gateway UDOT permit.pdf | 9/20/2023 | ||
Revision Gateway UDOT permit.pdf | 9/20/2023 | ||
Revision UDOT Permit extension.docx | 7/28/2023 | ||
Revision Gateway Estates UDOT Variance Approval.pdf | 6/14/2023 | ||
Revision 2023.6.9 Fire Exhibit.pdf | 6/9/2023 | ||
Original 52010.pdf | 5/9/2023 | ||
Preapplication Meeting Notes | |||
Original Pre app notes for Phase1A.docx | 5/9/2023 | ||
Proposed Final Plat | |||
Revision 2023.9.19 Phase 1A Final Plat.pdf | 9/19/2023 | ||
Revision 2023.7.28 Gateway Estates Subdivision Phase 1A.pdf | 7/31/2023 | ||
Revision 2023.7.3 Gateway Estates 1A Plat.pdf | 7/3/2023 | ||
Revision 2023.6.28 Gateway Estates Phase 1A.pdf | 6/29/2023 | ||
Original 2023.5.9 Gateway 1A.pdf | 5/9/2023 | ||
Proposed Preliminary Plan | |||
Revision 2023.5.25 Gateway Overall Prelim.pdf | 5/25/2023 | ||
Public Street Connectivity Plan | |||
Original Pre app notes for Phase1A.docx | 5/9/2023 | ||
Receipt | |||
Response to Review Agencies | |||
Secondary Water Will-Serve | |||
Septic Feasibility | |||
Revision Gateway Estates Phase 1A.pdf | 7/7/2023 | ||
Revision Updated LOF.pdf | 7/7/2023 | ||
Original Gateway Estates Phase 1,Septic LOF.pdf | 5/9/2023 | ||
Sewer Will-Serve | |||
Staff Report | |||
Time Extension | |||
Title Report | |||
Original Stewart 2021 Commitment.PDF | 5/9/2023 | ||
Traffic Study/Plan | |||
Well Approval | |||
Original E6148.pdf | 5/9/2023 | ||
Original E6224.pdf | 5/9/2023 | ||
Original E6225 (1).pdf | 5/9/2023 | ||
Original E6225.pdf | 5/9/2023 | ||
Original E6226(1).pdf | 5/9/2023 | ||
Original E6226(2).pdf | 5/9/2023 | ||
Original E6227.pdf | 5/9/2023 | ||
Original E6228.pdf | 5/9/2023 | ||
Original E6229.pdf | 5/9/2023 | ||
Original E6230.pdf | 5/9/2023 | ||
Original E6231.pdf | 5/9/2023 | ||
Original E6232.pdf | 5/9/2023 | ||
Uncategorized Documents | |||
Review 20230731_40-23_4th Redline_GATEWAY ESTATES SUBDIVISION PHASE 1A_6N2E11 SOUTH.pdf | 8/2/2023 | ||
Review 20230703_40-23_3rd Redline_GATEWAY ESTATES SUBDIVISION PHASE 1A_6N2E11 SOUTH.pdf | 7/12/2023 | ||
Review 20230525_40-23_1st Redline_GATEWAY ESTATES SUBDIVISION PHASE 1A_6N2E11 SOUTH.pdf | 6/7/2023 |
To access review documents, click on the individual review and the corresponding review documents will be listed under the review.
Engineering Review |
Approved |
Weber County Engineering | Tucker Weight | 11/29/2023 |
Survey 4th Final Review |
Conditional |
Weber County Surveyor's Office | Darrel Woodruff | 10/4/2023 |
Planning Review #2 |
Conditional |
Weber County Planning | Tammy Aydelotte | 9/20/2023 |
Survey 3rd Final review |
Conditional |
Weber County Surveyor's Office | Darrel Woodruff | 8/2/2023 |
Engineering Review |
Not Approved |
Weber County Engineering | Tucker Weight | 7/20/2023 |
Survey 2nd Final Review |
Not Approved |
Weber County Surveyor's Office | Darrel Woodruff | 7/31/2023 |
Environmental Health Sub Septic review |
Approved |
Weber-Morgan Health Department | Summer Day | 3/1/2024 |
Engineering Review |
Not Approved |
Weber County Engineering | Tucker Weight | 6/28/2023 |
Planning Review #1 |
Not Approved |
Weber County Planning | Tammy Aydelotte | 6/14/2023 |
Survey 1st Final Review |
Not Approved |
Weber County Surveyor's Office | Darrel Woodruff | 6/7/2023 |
Fire - DR |
Approved |
Weber Fire District | David Reed Weber Fire District | 8/22/2023 |
All followers will be notified of new documents, comments, and reviews to the project.
Name | Date Added |
Options
|
---|---|---|
Marta Borchert | 5/9/2023 | |
Steve Burton | 5/9/2023 | |
Steve Collier | 5/25/2023 | |
Summer Day | 5/25/2023 | |
Ronald Gleason | 5/16/2023 | |
Mandy Madrid | 11/22/2023 | |
Aric Manning | 5/25/2023 | |
Chad Meyerhoffer | 5/25/2023 | |
Bahy Rahimzadegan | 5/25/2023 | |
Emilee Roche | 5/9/2023 | |
Karl Sewell | 5/25/2023 | |
Jared Taylor | 5/25/2023 | |
David Reed Weber Fire District | 5/25/2023 | |
Tucker Weight | 5/25/2023 | |
Nate Wood | 5/25/2023 | |
Darrel Woodruff | 5/25/2023 | |
Greg Wright | 5/25/2023 |
List of estimated fees for this project.
Comments
Have a question? Leave a comment, your comment will be emailed to all project followers.
Tucker,
The improvement plans uploaded have all the changes made per your comments. I have uploaded a new plat per your comments.
I have added the invoice, once it is paid please let me know so we can mark the application as complete.