Preliminary 7 Lot Subdivision located in the Summit Eden Phase 1C amending Development Parcel D8. Culinary and Wastewater will be provided by Powder Mountain Water & Sewer District. This application will be reviewed as a final subdivision due to it being an amendment.
Parcel Number |
---|
231460001 - County Map |
Building Description | Square Feet | Valuation |
---|
Contractor Type | Name | Contact | Address |
---|
List of project documents. Review documents can be found under the Review tab.
Document | Date Uploaded |
Options
|
||
---|---|---|---|---|
Annexation Plat | ||||
Application | ||||
Attestation | ||||
Cost Estimate | ||||
Culinary Water Will-Serve | ||||
Engineered Plans | ||||
Final Recorded Plat | ||||
Geologic Hazards Evaluation | ||||
Geotechnical Evaluation | ||||
Notice of Decision | ||||
Open Space Preservation Plan | ||||
Other | ||||
Original Summit_Eden_Ph_1C_Amd_7_Recorded_Subdivision_Plat.pdf | 8/28/2018 | |||
Review 8-21-18_CC_Staff_Report-Summit_Eden_Phase_1C_Amd_7.pdf | 8/16/2018 | |||
Review 5-22-18_OVPC_Staff_Report_-_Summit_Eden_Phase_1C_Amendment_7.pdf | 5/14/2018 | |||
Original 5-11-18_Lot_151_Average_Slope_Check-Model.pdf | 5/11/2018 | |||
Original 5-11-18_Summit_Eden_Ph_1C_Amd_7_Plat.pdf | 5/11/2018 | |||
Original 5-9-18_VN_West_Laterals_Exhibit.pdf | 5/10/2018 | |||
Original VN_West_Laterals_Exhibit.pdf | 5/9/2018 | |||
Original 5-4-18_Ph1C_Amd7_plat.pdf | 5/8/2018 | |||
Review 20180507_Summit_Eden_Ph_1C_Amd_7_2nd_Submittal.pdf | 5/7/2018 | |||
Review 20180412_Summit_Eden_Ph1C_Amd_7_1st_Review.pdf | 5/1/2018 | |||
Review SPR_-Summit_Eden_Phase_1C_Amendment_7.pdf | 4/26/2018 | |||
Original Feasibility_Letter.pdf | 4/23/2018 | |||
Original Ph1C_Amd7_plat_20180403.pdf | 4/12/2018 | |||
Original Ph1C_Amd7_title_report_20180314.pdf | 4/12/2018 | |||
Original Ph1C_Amd7_geotech_and_geology_20170120.pdf | 4/12/2018 | |||
Original Ph1C_Amd7__application_UVS041218.pdf | 4/12/2018 | |||
Preapplication Meeting Notes | ||||
Proposed Final Plat | ||||
Proposed Preliminary Plan | ||||
Public Street Connectivity Plan | ||||
Receipt | ||||
Response to Review Agencies | ||||
Secondary Water Will-Serve | ||||
Septic Feasibility | ||||
Sewer Will-Serve | ||||
Staff Report | ||||
Time Extension | ||||
Title Report | ||||
Traffic Study/Plan | ||||
Well Approval | ||||
Uncategorized Documents |
To access review documents, click on the individual review and the corresponding review documents will be listed under the review.
Staff Report to Western Weber County Commission |
Approved |
N/A | N/A | 8/28/2018 |
Staff Report to the Ogden Valley Planning Commission |
Approved |
N/A | N/A | 5/22/2018 |
Engineering Review 3 |
Approved |
Braden Felix | 5/9/2018 | |
Engineering Review 2 |
Not Approved |
Braden Felix | 5/8/2018 | |
Survey 2nd review |
Approved |
Weber County Surveyor's Office | Steve Collier | 8/29/2018 |
Engineering Review 1 |
Not Approved |
Braden Felix | 5/1/2018 | |
Survey 1st Review |
Not Approved |
Weber County Surveyor's Office | Steve Collier | 5/1/2018 |
Weber Fire District |
Approved |
Weber Fire District | David Reed Weber Fire District | 4/26/2018 |
PROPERTY TAXES |
Approved |
Shirley Robinson | 7/31/2018 |
All followers will be notified of new documents, comments, and reviews to the project.
Name | Date Added |
Options
|
---|---|---|
Brett Badley | 1/1/0001 | |
Steve Collier | 1/1/0001 | |
Rick Everson | 1/1/0001 | |
Braden Felix | 1/1/0001 | |
Shirley Robinson | 1/1/0001 | |
David Reed Weber Fire District | 1/1/0001 |
List of all invoices tied to project.
List of estimated fees for this project.
Comments
Have a question? Leave a comment, your comment will be emailed to all project followers.