Parcel Number |
---|
200080017 - County Map |
Building Description | Square Feet | Valuation |
---|
Contractor Type | Name | Contact | Address |
---|
List of project documents. Review documents can be found under the Review tab.
To access review documents, click on the individual review and the corresponding review documents will be listed under the review.
Surveyor's 5th Review |
Approved |
Public | Shaun Rose | 8/18/2021 |
Address 2nd Review |
Approved |
Public | Shaun Rose | 8/18/2021 |
Surveyor's 4th Review |
Not Approved |
Public | Shaun Rose | 4/28/2021 |
Surveyor's 3rd Review |
Not Approved |
Public | Shaun Rose | 4/12/2021 |
Addressing Review #2 |
Not Approved |
Weber County Surveyor's Office | Brett Badley | 4/6/2021 |
Environmental Health Sewer |
Approved |
Weber-Morgan Health Department | Summer Day | 4/6/2021 |
Engineering Review |
Conditional |
Weber County Engineering | Tucker Weight | 3/31/2021 |
Engineering Review |
Not Approved |
Weber County Engineering | Tucker Weight | 1/26/2021 |
Planning Review #2 |
Recommend Approval with Conditions |
Weber County Planning | Scott Perkes | 1/26/2021 |
Surveyor's 2nd Review |
Not Approved |
Public | Shaun Rose | 1/20/2021 |
Addressing Review #1 |
Not Approved |
Weber County Surveyor's Office | Brett Badley | 11/12/2020 |
Engineering Review |
Not Approved |
Weber County Engineering | Tucker Weight | 11/3/2020 |
Planning Review #1 |
Not Approved |
Weber County Planning | Scott Perkes | 10/23/2020 |
Surveyor's 1st Review |
Not Approved |
Public | Shaun Rose | 10/16/2020 |
Fire Review |
Conditional |
Weber Fire District | David Reed Weber Fire District | 2/17/2021 |
All followers will be notified of new documents, comments, and reviews to the project.
Name | Date Added |
Options
|
---|---|---|
Scott Braeden | 9/28/2020 | |
Brett Bunderson | 9/28/2020 | |
Steve Burton | 9/28/2020 | |
Steve Collier | 9/28/2020 | |
Brian Cowan | 9/28/2020 | |
Summer Day | 9/28/2020 | |
Robert Fuller | 2/26/2021 | |
Michela Harris | 9/28/2020 | |
Craig Jorgensen | 9/28/2020 | |
Ryan Klinge | 1/24/2022 | |
Chad Meyerhoffer | 9/28/2020 | |
Garrett Nord | 5/16/2021 | |
Ruby Raccasi | 5/5/2021 | |
Bahy Rahimzadegan | 9/28/2020 | |
David Reed Weber Fire District | 9/28/2020 | |
Tucker Weight | 9/28/2020 |
List of all invoices tied to project.
List of estimated fees for this project.
Comments
Have a question? Leave a comment, your comment will be emailed to all project followers.
The applicant has submitted an updated final plat. All agencies please review for compliance with any outstanding comments or conditions.
Scott Perkes
This project was approved during the 5/14/2021 Administrative Review Meeting. A formal Notice of Decision has been uploaded to the Documents tab along with a signed copy of the staff report by the Planning Director.
The applicant has submitted an updated plat (dated 04/26/2021) addressing agency review comments. The applicant has also submitted a narrative document addressing Surveying's last redlined review comments. All agencies please reciew for compliance.
The applicant has submitted an updated final plat for agency review. All agencies please review for compliance with any remaining conditions/comments/. The applicant has also submitted a site plan that depicts the proposed location of a home and septic system to help in the reviewing of septic feasibility.
The applicant has submitted an updated plat. This plat has been uploaded under the file name "Ritter Ranch Subdivision 01152021". All agencies please review for compliance with outstanding review comments.
The Alternative Access Exception application has been submitted and will be reviewed and approved in tandem with this subdivision application. The name of this project in Frontier is "Fuller Robert-Alternate Access Exception" and can be found through the following link: https://frontier.co.weber.ut.us/p/Project/Index/11987
Engineering will post a review once the Alternative Access application is submitted and approved.
The applicant has been asked to submit and Alternative Access Exemtion application to service the proposed flag lot. The applicant has also been asked to submit a secondary water will-serve letter. These two items will need to be received prior to scheduling for Administrative Review.