Parcel Number |
---|
224100004 - County Map |
Building Description | Square Feet | Valuation |
---|
Contractor Type | Name | Contact | Address |
---|
List of project documents. Review documents can be found under the Review tab.
Document Name | Date Uploaded |
Options
|
|
---|---|---|---|
Annexation Plat | |||
Application | |||
Attestation | |||
Cost Estimate | |||
Culinary Water Will-Serve | |||
Original 19-Shaw Well Doc.pdf | 8/4/2023 | ||
Engineered Plans | |||
Revision 2023.12.07 8228-01 Hadlock Subdivision.pdf | 12/20/2023 | ||
Revision 2023.09.18 8228-01 Hadlock Subdivision.pdf | 9/22/2023 | ||
Final Recorded Plat | |||
Geologic Hazards Evaluation | |||
Geotechnical Evaluation | |||
Notice of Decision | |||
Revision Hadlock Subdivision 2nd Amendment Notice of Decision.pdf | 1/3/2024 | ||
Revision 2023 AR December 20 Adm Review Minutes.docx.pdf | 12/27/2023 | ||
Open Space Preservation Plan | |||
Other | |||
Preapplication Meeting Notes | |||
Revision Pre-Application Notes.pdf | 9/8/2023 | ||
Original Road connection.pdf | 8/4/2023 | ||
Proposed Final Plat | |||
Revision 2024.05.01 Final Plat.pdf | 5/29/2024 | ||
Revision 2024.2.14 Hadlock 2nd Amendment.pdf | 2/14/2024 | ||
Revision 2024.02.01 Final Plat.pdf | 2/6/2024 | ||
Revision 2023.12.07 Final Plat.pdf | 12/7/2023 | ||
Revision 2023.9.19 Final Plat.pdf | 9/22/2023 | ||
Revision Proposed Final Plat_09.09.23.pdf | 9/8/2023 | ||
Proposed Preliminary Plan | |||
Public Street Connectivity Plan | |||
Original Road connection.pdf | 8/4/2023 | ||
Receipt | |||
Response to Review Agencies | |||
Secondary Water Will-Serve | |||
Septic Feasibility | |||
Revision Hadlock 2nd amend.pdf | 6/4/2024 | ||
Original Weber Health.pdf | 8/4/2023 | ||
Sewer Will-Serve | |||
Staff Report | |||
Revision UVH091423 sr 2nd Approval.pdf | 2/6/2024 | ||
Time Extension | |||
Title Report | |||
Revision Title Commitment - Sep 13th, 11_56 AM.pdf | 9/14/2023 | ||
Revision Title Commitment - Sep 13th, 11_56 AM.pdf | 9/14/2023 | ||
Original Title Report Liberty.pdf | 8/4/2023 | ||
Traffic Study/Plan | |||
Well Approval | |||
Revision Pump Test Results.pdf | 5/29/2024 | ||
Original 19-Shaw Well Doc.pdf | 8/4/2023 | ||
Uncategorized Documents | |||
Review 20240212_93-23_(FOURTH REDLINE)_HADLOCK SUBDIVISION-2ND AMENDMENT_AMENDING PARCEL A .pdf | 2/14/2024 | ||
Review 20240206_93-23_(THIRD REDLINE)_HADLOCK SUBDIVISION-2ND AMENDMENT_AMENDING PARCEL A .pdf | 2/7/2024 | ||
Review 20231207_93-23_(SECOND REDLINE)_HADLOCK SUBDIVISION-2ND AMENDMENT_AMENDING PARCEL A .pdf | 12/20/2023 | ||
Review 20230922_93-23_(FIRST REDLINE)_HADLOCK SUBDIVISION-2ND AMENDMENT_AMENDING PARCEL A .pdf | 9/26/2023 |
To access review documents, click on the individual review and the corresponding review documents will be listed under the review.
Environmental Health |
Approved |
Weber-Morgan Health Department | Summer Day | 6/4/2024 |
Conditional #2 |
Recommend Approval with Conditions |
Weber County Planning | Tammy Aydelotte | 4/19/2024 |
Engineering Review |
Conditional |
Weber County Engineering | Tucker Weight | 2/27/2024 |
Surveyor's Fourth Review |
Approved |
Public | Shaun Rose | 2/14/2024 |
Surveyor's Third Review |
Not Approved |
Public | Shaun Rose | 2/7/2024 |
Planning Review |
Conditional |
Weber County Planning | Tammy Aydelotte | 2/6/2024 |
Engineering Review |
Not Approved |
Weber County Engineering | Tucker Weight | 1/12/2024 |
Fire - DR |
Approved |
Weber Fire District | David Reed Weber Fire District | 1/11/2024 |
Surveyor's Second Review |
Approved |
Public | Shaun Rose | 12/20/2023 |
Engineering Review |
Not Approved |
Weber County Engineering | Tucker Weight | 10/6/2023 |
Surveyor's First Review |
Not Approved |
Public | Shaun Rose | 9/26/2023 |
Jared Taylor - Weber Fire District |
Conditional |
Weber Fire District | Jared Taylor | 9/22/2023 |
All followers will be notified of new documents, comments, and reviews to the project.
Name | Date Added |
Options
|
---|---|---|
Marta Borchert | 8/4/2023 | |
Sidney Bowen | 9/21/2023 | |
Steve Burton | 8/4/2023 | |
Thomas Butler | 8/4/2023 | |
Steve Collier | 9/14/2023 | |
Jeremy Draper | 10/31/2023 | |
Jason Felt | 10/31/2023 | |
Jami Hadlock | 1/29/2024 | |
Alec Hansel | 9/14/2023 | |
Mandy Madrid | 11/22/2023 | |
Aric Manning | 9/14/2023 | |
Chad Meyerhoffer | 9/14/2023 | |
Bahy Rahimzadegan | 9/14/2023 | |
Shaun Rose | 9/14/2023 | |
Karl Sewell | 9/14/2023 | |
Jared Taylor | 9/14/2023 | |
David Reed Weber Fire District | 9/14/2023 | |
Tucker Weight | 9/14/2023 | |
Nate Wood | 9/14/2023 | |
Greg Wright | 9/14/2023 |
List of estimated fees for this project.
Comments
Have a question? Leave a comment, your comment will be emailed to all project followers.
The Surveyors Office has change this project to (not approved) due to the fire turn-around/ 20' right of way being added to the plat. Dimensions will need to be shown on the plat for the (fire turn around).
Invoice created, once the fee is paid application can be accepted for review
Please upload a title report dated within 30 days.
Please submit an engineered plat