Karl Lundin Hillside Review

Address:
2292 Panorama Circle, Liberty, UT, 84310
Maps:
Project Type:
Hillside Reviews
Sub Type:
Hillside Reviews
Created By:
Created On:
7/7/2015
Project Status:
Rejected
Status Date:
5/25/2017
File Number:
HSR 2015-02
Project Manager

Application

To construct single family dwelling 2/septic system on property as shown on site plans.  Property is heavily wooded and will be kept as much so as possible.  This application has been withdrawn by the applicant.  This file is closed.


Property Address
2292 Panorama Circle
Liberty, UT, 84310

Property Owner

--

Representative

--

False
0
,

Parcel Number

Building Description Square Feet Valuation

Contractor Type Name Contact Address


Documents

List of project documents. Review documents can be found under the Review tab.

Document Name Date Uploaded
Options
Engineered Plans
Geologic Hazards Report
Geotechnical Report
Landscaping Plan
Notice of Decision
Other
Original Review_Comments_-_Geologic_Hazards_Report.pdf 3/14/2016
Original 2030-01N-15_Lot_23_Big_Sky_Estates_Geologic_Hazards_Evaluation.pdf 3/3/2016
Original GBES_Project_Memo_1-27-2016.pdf 1/28/2016
Original Final_GBES_Project_Memo_Big_Sky_Lot_23_12-22-2015.pdf 1/4/2016
Original SA_Project_Meeting_Memos_Lot_23_Big_Sky_Estates_Scoping_08-12-15.pdf 8/17/2015
Original 070215-PANORAMA.pdf 7/9/2015
Original Lundin_Karl_LOFrevised2015.docx 7/8/2015
Original Geotechnical_Lot_23_Big_Sky_Estates_No_1.pdf 7/7/2015
Original Hillside_Review_Application.pdf 7/7/2015
Planning Staff Report
Site Plan
Uncategorized Documents

Comments

Have a question? Leave a comment, your comment will be emailed to all project followers.

N/A - 5/25/2017
This application has been withdrawn by the applicant. This file is closed.
Angela Martin - 9/6/2016
The Contractor is no longer doing this project.
N/A - 8/17/2015
A meeting note has been added as a file. The meeting included geologists, engineerings, developer, and county staff.
Dana Shuler - 7/30/2015
A geologic study is required. Please contact me to set up a scoping meeting. 801-399-8761
Dana Shuler - 7/15/2015
Lot 23 Big Sky Estates, Phase 1

Reviews

To access review documents, click on the individual review and the corresponding review documents will be listed under the review.

Engineering Review 1

Not Approved

Dana Shuler 12/11/2015
Weber Fire District Review

Not Approved

N/A N/A 9/9/2015

Followers

All followers will be notified of new documents, comments, and reviews to the project.

Name Date Added
Options
Jared Andersen 1/1/0001
Andrew Harris 1/1/0001
Elliott Lips 1/1/0001
Karl Lundin 1/1/0001
Dana Shuler 1/1/0001
David Simon 1/1/0001
Alan Taylor 1/1/0001

Payments

List of all invoices tied to project.