Parcel Number |
---|
231380003 - County Map |
Building Description | Square Feet | Valuation |
---|
Contractor Type | Name | Contact | Address |
---|
List of project documents. Review documents can be found under the Review tab.
Document Name | Date Uploaded |
Options
|
|
---|---|---|---|
Annexation Plat | |||
Application | |||
Revision Project Narrative.pdf | 4/8/2021 | ||
Attestation | |||
Cost Estimate | |||
Culinary Water Will-Serve | |||
Revision Water-Sewer Commitment_20210406.pdf | 4/19/2021 | ||
Engineered Plans | |||
Final Recorded Plat | |||
Revision final recorded.pdf | 7/6/2021 | ||
Geologic Hazards Evaluation | |||
Original GeoHazards.pdf | 3/25/2021 | ||
Geotechnical Evaluation | |||
Notice of Decision | |||
Open Space Preservation Plan | |||
Other | |||
Preapplication Meeting Notes | |||
Proposed Final Plat | |||
Revision Final Plat_20210527.pdf | 5/28/2021 | ||
Original Final Plat_20210323.pdf | 3/25/2021 | ||
Proposed Preliminary Plan | |||
Original Prelim Plat_20210303.pdf | 3/25/2021 | ||
Public Street Connectivity Plan | |||
Receipt | |||
Revision Receipt.pdf | 4/6/2021 | ||
Response to Review Agencies | |||
Secondary Water Will-Serve | |||
Septic Feasibility | |||
Sewer Will-Serve | |||
Staff Report | |||
Revision signed report.pdf | 7/2/2021 | ||
Time Extension | |||
Title Report | |||
Revision Title Rpt L40062PM-INFO(GT-ORT)(DevParcelD6, 23-138-0003,Info)Amd1.PDF | 3/26/2021 | ||
Original Title Report.PDF | 3/25/2021 | ||
Traffic Study/Plan | |||
Well Approval | |||
Uncategorized Documents | |||
Review 20210528_(Second submittal) Summit Eden Phase ID Amendment 3 Amending Parcel D6 Summit Eden PH 1D Amendment I - Copy.pdf | 6/1/2021 | ||
Review Address 1st Review.pdf | 5/25/2021 | ||
Review 202104_(first submittal) Summit Eden Phase ID Amendment 3 Amending Parcel D6 Summit Eden PH 1D Amendment I - Copy.pdf | 5/17/2021 |
To access review documents, click on the individual review and the corresponding review documents will be listed under the review.
Address 2nd Review |
Approved |
Public | Shaun Rose | 6/1/2021 |
Surveyor's 2nd Review |
Approved |
Public | Shaun Rose | 6/1/2021 |
Address 1st Review |
Not Approved |
Public | Shaun Rose | 5/25/2021 |
Engineering Review #2 |
Approved |
Weber County Engineering | Ashley Thoman | 5/24/2021 |
Surveyor's 1st Review |
Not Approved |
Public | Shaun Rose | 5/17/2021 |
Address 1st Review |
Not Approved |
Public | Shaun Rose | 5/17/2021 |
Engineering Review #1 |
Conditional |
Weber County Engineering | Ashley Thoman | 5/5/2021 |
Fire Review |
Conditional |
Weber Fire District | David Reed Weber Fire District | 4/15/2021 |
All followers will be notified of new documents, comments, and reviews to the project.
Name | Date Added |
Options
|
---|---|---|
Steve Burton | 3/25/2021 | |
Steve Collier | 3/25/2021 | |
Rick Everson | 10/27/2021 | |
Aric Manning | 3/25/2021 | |
Bahy Rahimzadegan | 3/25/2021 | |
Ashley Thoman | 4/6/2021 | |
David Reed Weber Fire District | 3/25/2021 |
List of all invoices tied to project.
List of estimated fees for this project.
Comments
Have a question? Leave a comment, your comment will be emailed to all project followers.
Once the application is complete. The surveyor's office will begin the review process.
Spoke to applicant 3/26/2021 and they were notified that once payment is received application can be accepted.