2012 Sidewalk & Roadway Repair

Address:
Various Locations, Unincorporated Weber County, UT,
Maps:
Project Type:
Engineering Projects
Sub Type:
Engineering Projects
Created By:
Created On:
4/23/2012
Project Status:
Submitted
Status Date:
4/23/2012
File Number:
2012-04
Project Manager

Application

This project is to repair portions of sidewalk, curb, gutter and roadways in various locations throughout the unincorporated areas of Weber County. Part of this project will include the waterway located at 5950 S Skyline Drive in Uintah.


Property Address
Various Locations
Unincorporated Weber County, UT,

Property Owner

--

Representative

--

False
0
,

Parcel Number

Building Description Square Feet Valuation

Contractor Type Name Contact Address


Documents

List of project documents. Review documents can be found under the Review tab.

Document Name Date Uploaded
Options
Other
Original nop_pentrex.pdf 12/17/2012
Original NOA_pentrex.pdf 12/17/2012
Original signed_NTP.pdf 10/25/2012
Original Performance_Bond.pdf 10/15/2012
Original cert_of_insur.pdf 10/15/2012
Original po_agreement.pdf 10/15/2012
Original signed_noa.pdf 10/9/2012
Original 2012_sidewalk__roadway_repair_project.pdf 10/3/2012
Original rochelles_bid_sheet.pdf 10/2/2012
Original triple_j_concrete.pdf 10/2/2012
Original wasatch_west_contracting.pdf 10/2/2012
Original zpsco_construct.pdf 10/2/2012
Original r.l_shaw.pdf 10/2/2012
Original quicksilver.pdf 10/2/2012
Original bid_list.pdf 10/2/2012
Uncategorized Documents

Comments

Have a question? Leave a comment, your comment will be emailed to all project followers.

N/A - 4/16/2013
I received another call from Carry at Phoenix Loss Control regarding the insurance for ZPSCO. I emailed it to her again.
N/A - 4/11/2013
Angela has requested a different type of invoice than what they sent us, so I emailed them asking for the invoice.
N/A - 4/2/2013
Pentrex completed their portion of the work over the weekend and have requested payment.
N/A - 3/7/2013
Dale with Penetrx called today and asked to be notified as soon as the gutters were swept. He will get the concrete sealed at that point. I spoke to Kelly, he said he'd look at it next week and see if it's ready.
N/A - 2/4/2013
Mike Hewit called and told me there is still too much snow for him to apply his product. He will keep watching and let me know as soon as he can do it. He asked about contact the neighbors, I told him to please do so when he was ready. He asked me to send over my bid package again.
N/A - 1/11/2013
I received an email yesterday from ZPSCO giving me "a heads up" on the claim for comcast
N/A - 1/7/2013
I just received a call from Kerry with Phoenix Loss Control on behalf of Comcast. She was calling about a claim filed by Comcast on a line that was cut during the installation of sidewalk in Uintah by our hired contractor, ZPSCO. She said she'd just gotten off the phone with Kim Smith, he admitted cutting the line and made sure she knew there was nothing the county could about it being as he's been paid. He was rude and cussed and screamed at her and said there was no way he was going to pay for it. She asked me to send her a copy of their certificate of liability insurance, which I did.
N/A - 1/3/2013
Mike just called and said he's looking at maybe this weekend or next weekend because it's been so cold. I told him that was fine and to keep me posted.
N/A - 1/3/2013
I sent a follow up email to Mike Hewitt to see if they've had a chance to apply their product or of the weather has been an issue for them.
N/A - 12/11/2012
Sent a follow up email to Dale at Pentrex today about the paperwork I sent him on November 28th.
N/A - 12/10/2012
ZPSCO has been paid. I'm waiting for Pentrex to sign the Notice and send it back to me.
N/A - 11/28/2012
Project was completed yesterday. I will do a final walk through and get a punch list put together. Also the contractor sent me the truck tickets and new invoice for the change order, I'm waiting for Jared to approve it. I put together a notice of Award and Notice to Proceed for Pentrex to do the sealing on the concrete 30 days from now.
N/A - 11/8/2012
Contractor has ran into areas of bad material and are having difficulty getting compaction. After a phone call with Jared it was decided they would over excavate the soft spots and place structural fill. I sent Kim an email authorizing this extra work. Contractor call me this morning and let me know he hit a gas line. I gave him a phone number for Questar.
N/A - 11/5/2012
I just spoke to the contractor, they will be moving in and starting tomorrow.
N/A - 10/25/2012
I received the signed Notice to Proceed today. Contractor indicated he will start this week when the weather turns good.
N/A - 10/17/2012
I spoke with dale from Pentrex today. He received my drawings, went out and measured the concrete and will be putting together a bid and emailing it to me to get approved. He said he was charging us $0.23 per foot.
N/A - 10/16/2012
On the 10th, I sent Dale at Pentrex a copy of all the drawings. Today he called and said he didn't receive them. I verified his email address and sent them to him again.
N/A - 10/16/2012
I did receive all the required documentation prior to the deadline. I will be setting up a pre-construction meeting in the next day or two.
N/A - 10/15/2012
I emailed ZPSCO today to remind them their performance and payment bonds are due by 5:00 today.
N/A - 10/9/2012
I received the signed Notice of Award today.
N/A - 10/4/2012
Bid was awarded to ZPSCO today.
N/A - 9/19/2012
Bid Opening is October 2nd
N/A - 9/14/2012
Bid package was delivered to purchasing today.
N/A - 8/21/2012
Drawings and Bid documents are done, waiting for CRS to review before sending out to bid
N/A - 8/15/2012
I just spoke to Kelly, he said he will be able to do the asphalt on this project.
N/A - 8/14/2012
I've heard back from Dan, he said I am okay to proceed as far as my budget is concerned. I've sent pdf's to Kelly to review and the bid documents to Jared to send to CRS for review.
N/A - 8/14/2012
Drawings, bid documents and cost estimate are done. Waiting for additional information from Dan Olsen and Kelly Hipwell before sending out to bid.
N/A - 7/27/2012
Today I received the field data on the 5150 S cul-de-sac from Larry
N/A - 7/16/2012
I have looked at Mr. Decker's sidewalk and it is not a trip hazard. I did send him a letter last year explaining that I couldn't get it fixed until I fixed the trip hazards in the county but that I would put it on my list of things to be looked at. I will go look at it again this year and see if anything has changed.
Michael Tuttle - 7/13/2012
I just got a call from Amy Joe in the Commission Office. She said there is a man by the name of Wayne Delker that has been trying to get his sidewalk repaired for 3 years. He said that his sidewalk has sunk. I'm not sure if there is a trip hazard, or if it's just sunk. His address is 2394 E 6150 S, and his phone is 801-479-4594.
N/A - 6/22/2012
I received a .csv file from Larry today with the centerline information on Skyline Drive and 5950 South
N/A - 6/21/2012
Larry sent Trevor out this morning to get a couple crown shots for me on the Skyline 5950 S Intersection. I asked Larry to survey the cul-de-sac at 2025 E 6175 S in Uintah, he indicated it would a month to get the Cad file. Zach is measuring lengths for me today.
N/A - 6/19/2012
Under the Americans with Disabilities Act (ADA), trip hazards are defined as a change in any vertical level over 1/4".
N/A - 6/19/2012
I received survey data from Larry yesterday and have been working on the intersection of Skyline Drive and 5950 South. The interns have taken photo's of what they were able to find that needed repair, I'm in the process of reviewing those.
N/A - 4/23/2012
Larry has been working on surveying the curb & gutter surrounding the failed waterway at 5950 S Skyline Drive in Uintah. I spoke to him about it this morning, he indicated he has roughly 200' of field work left to complete and is hopeful to get to it in the week or so. I will be walking the streets in Roy and Uintah to find areas in need of repair as I haven't had any complaints this year.

Reviews

To access review documents, click on the individual review and the corresponding review documents will be listed under the review.

Followers

All followers will be notified of new documents, comments, and reviews to the project.

Name Date Added
Options