Landslide & Roadway Repair

Address:
Moose Hollow Drive, Eden, UT,
Maps:
Project Type:
Engineering Projects
Sub Type:
Engineering Projects
Created By:
Created On:
9/2/2011
Project Status:
Submitted
Status Date:
3/22/2012
File Number:
2010-06
Project Manager

Application

The purpose of this project is to repair the damages sustained to the roadway and storm drain system as a result of a land slide. The land slide has been monitored through survey data for a couple of years and it has been determined that it is now stable. We will be installing high-back curb & gutter along the North slide of Moose Hollow Drive, adding a catch basin and repairing the associated piping.


Property Address
Moose Hollow Drive
Eden, UT,

Property Owner

--

Representative

--

False
0
,

Parcel Number

Building Description Square Feet Valuation

Contractor Type Name Contact Address


Documents

List of project documents. Review documents can be found under the Review tab.

Document Name Date Uploaded
Options
Other
Original punch_list.pdf 9/2/2011
Uncategorized Documents

Comments

Have a question? Leave a comment, your comment will be emailed to all project followers.

N/A - 5/3/2012
I met Kelly on site to see what is left to done on this project. he will installed the rip rap around the box and grade back of the new curb to make it look better. His department has already done the asphalt work. he asked me to talk to Thom about the box and water line which is constantly running.
N/A - 4/6/2012
Kelly and I will be looking at this site on Monday.
N/A - 3/30/2012
I met with Kelly and Nate about this project. Kelly said he would have it be one of the first projects he does this year before he gets to busy.
N/A - 3/22/2012
Spoke to Nate this afternoon, he'd like to set up a meeting with Kelly to discuss this project.
N/A - 10/17/2011
After reviewing the APWA Manual of Standards and Specifications it looks as though I need to give them 120 days from issuing the final punch list. November 7, 2011 I will visit the site for additional photo's and if nothing has changed I will issue the end of contract letter.
N/A - 9/2/2011
This project was started before Miradi. A design was completed and put out to bid September 2010. Eddy Shaw Construction was awarded the contract and worked on the improvements until the weather got to severe. At that time an invoice was submitted requesting payment for the entire contract. Due to the deep snow cover I wasn't able to verify the projects completion. I paid the contractor for the portions of the project I knew were completed and with held the remaining monies. March 22, 2011 the contractor emailed me asking about the remaining monies. I indicated that there were remaining items to be finished. June 16, 2011 the contractor emailed me again asking if the project was ready to the final payment. I did a site visit, took photo's and on July 6, 2011 I emailed the punch list. I have visited the site many times since then and no more work has been done. In August 2011, I spoke with Curtis about the situation and he indicated that I should give him 90 days from the date of the punch list to notify the contractor in writing that no more monies will be paid out on this contract and that we will be completing the project ourselves. That date is October 6, 2011.

Reviews

To access review documents, click on the individual review and the corresponding review documents will be listed under the review.